MRCB telah diberi kontrak beratus juta
ringgit untuk mengurangkan risiko banjir di Pahang. Projek ini
diberikan oleh Jabatan Pengairan dan Saliran sekitar muara Sg Pahang
dan persisiran pantai untuk mengurangkan risiko banjir ketika ombak
pasang besar dan sebagainya. Dapatkah MRCB buktikan yang projek
mereka Fasa 1 dan Fasa 2 tidak gagal kerana kini MRCB dapat pula
kontrak RM130 juta untuk Fasa 3? Harap Ahli Parlimen Pakatan Rakyat
dan BN dapat membangkitkan isu ini di Parlimen.
MRCB DAPAT PROJEK PEMULIHARAAN SUNGAI
PAHANG FASA 3 BERNILAI RM130 JUTA
30 Ogos 2013(Bernama) -- Malaysian
Resources Corporation Bhd (MRCB) memperoleh Projek Pemuliharaan Muara
Sungai Pahang Fasa 3 bernilai RM130 juta di Pekan, Pahang. Kontrak
itu diberikan oleh Jabatan Pengairan dan Saliran.
Kuala Sungai Pahang (Phase 1)
The project was implemented in phases
due to budget constraint. The main objectives can only be fulfilled
once the Project is fully implemented.
The main objectives of the overall
Project works are:
(i) To reduce the risk of coastal
flooding to Pekan town and the surrounding areas.
Nevertheless, MRCB completed the Phase
I works in December 2010 within 2 years contract period. For erosion
control at Sungai Pahang river bank, rock revetment was build to
dissipate high current velocity.
Kuala Sungai Pahang (phase 2)
Kuala Pahang Phase 2 works is carried
out to continue the construction of the completed Phase 1 works
without affecting the overall performance requirements of the full
design. The project is expected to commence later in July 2011 and
expected to complete in 18 months period.
The Phase 2 works will include:
(i) Partial construction of the
northern breakwaters and dykes (at the Kuala Pahang river mouth) with
the necessary temporary protection at the breakwater heads.
Another aspect of mitigation measures
to be carried out is coastal flooding at Pekan Town. A coastal
flooding study was also incorporated in the design of coastal
protection structure in Phase II works.